2008 Ring main western leg Runway to NFD offices - Completed £ 54,000
2009Construction of switching shed at site 70 - Completed £ 1,500Connection from shed 70 to Field of Dreams - Completed £ 4,500Installation of switching gear at shed 70 - Completed £ 4,000 Repair and tidy electrical boxes in Pineridge - Completed £ 3,000
2010 to 2014 (5 year project spending forecast) £ 177,000
2010 Installation of Pineridge breakers £ 2,500Repair and tidy electrical boxes in the Central area £ 4,000 Construction of switching shed at main gate £ 1,500Completion of ring main connections on CC road £ 4,000Upgrading earthing arrangements in Central area £ 1,000Contingency Fund – unforeseen works £ 6,000
2011 Installation of switching gear for main gate shed £ 9,000
2012Installation of new underground cable
(Main entrance – Phoenix - Site 70) £ 20,000
2013 Complete ring main connections £ 5,000
2014 Pineridge upgrade £ 30,000