New Findhorn Directions (NFD) Ltd

Park Electric - Maintainance & upgrades timetable and costs

2008   Ring main western leg Runway to NFD offices - Completed   £ 54,000  

2009Construction of switching shed at site 70 - Completed   £ 1,500Connection from shed 70 to Field of Dreams - Completed £ 4,500Installation of switching gear at shed 70 - Completed   £ 4,000  Repair and tidy electrical boxes in Pineridge - Completed   £ 3,000  

2010 to 2014 (5 year project spending forecast) £ 177,000 
2010 Installation of Pineridge breakers  £ 2,500Repair and tidy electrical boxes in the Central area  £ 4,000   Construction of switching shed at main gate     £ 1,500Completion of ring main connections on CC road £ 4,000Upgrading earthing arrangements in Central area £ 1,000Contingency Fund – unforeseen works   £ 6,000

2011 Installation of switching gear for main gate shed £ 9,000

2012Installation of new underground cable
  (Main entrance – Phoenix - Site 70)    £ 20,000

2013 Complete ring main connections   £ 5,000

2014 Pineridge upgrade   £ 30,000